Command Center
calendar_today Today: Sat, Oct 31, 2026Ong Residential
visibilityUtilized ₱3,345,050 (33%) of contract price
Realized ₱734,950 (24%) to date
- Total Inflow Collected
- + ₱4,080,000
- Total Outflows
- − ₱3,345,050
- Company Cash on Hand (Main Bank)
- ₱2,486,730
40% of the contract price collected so far
Weekly payroll runs · latest 5 shown
Paid expenses · latest 5 shown
Timeline & Cash Burn
On track151 days remaining in project cycle
-
Jun 29 M1 — Site Clearing & Layoutcheck
-
checkJul 06 M2 — Footing Excavation
-
Jul 13 M3 — Gravel Beddingcheck
-
checkJul 20 M4 — Footing & Column Rebar
-
Aug 01 M5 — Footing & Pedestal Pouringcheck
-
checkAug 06 M6 — Foundation & Tie Beams
-
Aug 11 M7 — Septic Tankcheck
-
checkAug 18 M8 — Raised Ground-Floor Fill
-
Aug 25 M9 — Ground-Floor Slabcheck
-
checkSep 08 M10 — Ground-Floor Columns
-
Sep 22 M11 — Ground-Floor CHB Wallscheck
-
checkOct 13 M12 — Second-Floor Beams
-
Nov 07 · Now Second-Floor Slab
-
Mar 31 M14 — Roofing, Finishes & Turnover
Swipe to see all milestones →
Active Tasks
In progress · soonest due first
Second-floor slab rebar inspection
PROrder ready-mix concrete for slab pour
RSInstall second-floor shoring
RSLatest Site Progress
Daily work logs and progress updates from the field
-
Oct 31, 2026 • Today • Daily Work Log
+4 photos
Second-floor slab rebar tying, about 60% done.
RS Ruben Santos -
Oct 30, 2026 • 1 day ago • Daily Work Log
+2 photos
Slab formworks installed on grids A–C.
RS Ruben Santos -
Oct 28, 2026 • 3 days ago • Progress Update
+5 photos
Ground-floor CHB walls completed. Second-floor slab preparation started.
PR Engr. Paolo Reyes -
Oct 26, 2026 • 5 days ago • Daily Work Log
+1 photos
Scaffolding and shoring posts installed.
RS Ruben Santos -
Oct 24, 2026 • 1 week ago • Daily Work Log
+3 photos
Gravel and sand delivery received and checked.
RS Ruben Santos